Singapore HDB Restoration Day 74 – Woodworking Functions Completed, Paint Functions On-going
Day 74 of restoration
Singapore 5-room resale HDB restoration
Day 1 – 3 : Hack
Day 5 – 19 (2 weeks) : Tiling (Living area, rooms, kitchen area, restroom)
Day 20 : Commode Doors, Commode Add-on Marking
Day 23 : 1st Paint Day (Ceiling, living area, bed spaces) + Gas Pipeline Setup, Dismantled Gas Meter
Day 26 : Paint (incorrect colour??), room doors & maindoor setups, examine existing air-con piping (to re-lay 3 days later on as existing piping is obstructing the recently hacked entrance)
Day 29 : Air-conditional (supply work & product to mount Mitsubishi 10k solitary Starmex Inverter split-type a/c unit, remodel system 3 piping for existing a/c, 2 years service warranty)
Day 29 Evening : Arrival of commode vanity bought from Ezbuy (60cm and also 70cm)
Day 31 : Plumbing technician mounted commode vanity, mirror cupboard, container, bidet spray, instantaneous heating system, various other commode devices. Examination water stress of the hot water heater. To alter typical restroom mixer later on. Painter remedying living area and also rooms wall surface Nippon paint to snow white. Set up cleaning device pipeline and also snowy faucet. ID sent out woodworking jobs dimension today, to examine and also validate design after that can begin make.
Day 34 : A lot of illumination jobs (transformed from square downlight to round downlight) are done other than those in kitchen area and also bedroom (assumption is waiting on woodworking functions – kitchen area cupboard, master closet), frameless (we assumed is black framework) set panel was mounted. Opennet moving and also information factor.
Day 36: Send out the food preparation hob & hood over, purchased a collection of Aerogaz food preparation Hood & Hob at much less than $500. Obtained a cost-effective brand name and also version, unsure if we will certainly prepare often. Design: Hood AZ-9100 Black, Year 2021 New, Touch Panel, No switches, 900mm, coupled with Hob 790×500, black, solidified glass
Day 38: Consult ID when can done and also handover (A: another month to finish all and also handover) Idea it will certainly be done quickly given that progression rather well. Think the hold-up is because of Covid-19 scenario so woodworking job is postponed. No option however to wait… … …
Day 39 : Send out the black mixer and also black pipe over, to change the existing one (silver colour) in the typical restroom. New electric job done: changed the power indicate the left (as well near the hood), changed master area brand-new power factor wire place, hid brand-new information factor electrical wiring. Step footwear shelf, cupboard and also drape track size.
Day 42 : Send out added restroom devices over. Preparation not to see that constant hereafter given that it require another month to obtain the restoration done… (ADD: DIDN’T KNOW THAT I WILL CERTAINLY MARVEL IN THE FOLLOWING CHECK OUT). Asked ID to take down the existing buzzer. Kitchen area cupboard interior PVC selected earlier runs out supply, re select one… On-going paint jobs
Day 47 : Last gone to 5 days earlier. Rather unexpected when I come today. Flooring defense paper was eliminated, particles was removed, basic cleansing is finished……Seem like relocating currently!!! Scent major door paint, must be doing paint functions today…
Day 48 : Come with daytime today to examine the floor tile grouting, a whole lot obtained cleaned off after the cleansing. Planned to do noting however there are a lot of… might obtain the ID / professional to examine their very own… plaster retouch is provided for some small split at restroom box-up.
Day 49 : Send out the ceiling repaired fabric drying out devices over so they can assist to take down the existing one and also alter to a brand-new set
Day 53 : No additional progression
Day 54 : No even more proceed, go and also validate the inclined bedframe dimension, examine the frozen glass sticker label dimension, drape track dimension, as well as additionally art paint dimension~
Day 58 : Send out the boom sanctuary T-catch door magnet there, to change. run into the ID~ he stated 1 or 2 even more weeks can obtain the woodworking functions done, making currently. To retouch paint, recheck grouting, eliminate existing steel door lock as well as additionally take down the existing buzzer outlet.
Day 67 : didnt came right here for a long time as a result of waiting on woodworking manufacture, remarkably, those products are right here and also 50% of the woodworking functions is finished.
Day 68 : Gas pipeline, check hot water heater with power on, go IKEA, no ideal drape size, obtained a collection of white large drapes, foam bed mattress, mirror and also a few other things invested overall SGD 200+
Day 70: Distribution of M1 Asus router, get television at Courts. Called ID to examine approximated conclusion day, required another month. Emphasized on conclusion within 2 weeks. Required to move-in.
Day 72 : Acquire entrance paint product
Day 74 : Woodworking functions is finished today. Very first time fulfill painter in your home
No modifying, real illumination in your home.