Singapore HDB Improvement Day 34 – Set Up Lightings & Restroom Fixed Panel, Information Factor



Day 34 of improvement
Improvement Day Thirty-Four
Singapore 5-room resale HDB improvement

Day 1 – 3 : Hack
Day 5 – 19 (2 weeks) : Tiling (Living area, bed rooms, cooking area, washroom)
Day 20 : Bathroom Doors, Bathroom Add-on Marking
Day 23 : 1st Paint Day (Ceiling, living area, bed spaces) + Gas Pipeline Setup, Dismantled Gas Meter
Day 26 : Paint (incorrect colour??), room doors & maindoor installments, examine present air-con piping (to re-lay 3 days later on as present piping is obstructing the freshly hacked entrance)
Day 29 : Air-conditional (supply work & product to set up Mitsubishi 10k solitary Starmex Inverter split-type a/c, renovate system 3 piping for existing a/c, 2 years service warranty)
Day 29 Evening : Arrival of bathroom vanity bought from Ezbuy (60cm as well as 70cm)
Day 31 : Plumbing technician set up bathroom vanity, mirror closet, container, bidet spray, instantaneous heating unit, various other bathroom devices. Examination water stress of the hot water heater. To transform usual washroom mixer later on. Painter correcting living area as well as bed rooms wall surface Nippon paint to snow white. Set up cleaning device pipeline as well as snowy faucet. ID sent out woodworking jobs dimension today, to examine as well as validate format after that can begin produce.
Day 34 : A lot of illumination jobs (transformed from square downlight to round downlight) are done other than those in cooking area as well as bedroom (assumption is waiting on woodworking functions – cooking area closet, master closet), frameless (we assumed is black framework) set panel was set up. Opennet moving as well as information factor.

No modifying, real illumination in your home.

Resale Apartment

Please strike the subscribe switch as well as similar to this video clip. thanks