Singapore HDB Restoration Day 48 (Day Time) – Examine grouting
Day 48 of remodelling
Restoration Day Forty-Eight
Singapore 5-room resale HDB remodelling
Day 1 – 3 : Hack
Day 5 – 19 (2 weeks) : Tiling (Living area, bed rooms, kitchen area, shower room)
Day 20 : Commode Doors, Commode Add-on Marking
Day 23 : 1st Paint Day (Ceiling, living area, bed areas) + Gas Pipeline Setup, Dismantled Gas Meter
Day 26 : Paint (incorrect colour??), bed room doors & maindoor setups, examine existing air-con piping (to re-lay 3 days later on as existing piping is obstructing the freshly hacked entrance)
Day 29 : Air-conditional (supply work & product to mount Mitsubishi 10k solitary Starmex Inverter split-type air conditioning unit, remodel system 3 piping for existing a/c, 2 years service warranty)
Day 29 Evening : Arrival of commode vanity bought from Ezbuy (60cm and also 70cm)
Day 31 : Plumbing mounted commode vanity, mirror cupboard, container, bidet spray, immediate heating unit, various other commode devices. Examination water stress of the hot water heater. To alter usual shower room mixer later on. Painter correcting living area and also bed rooms wall surface Nippon paint to snow white. Mounted cleaning equipment pipeline and also snowy faucet. ID sent out woodworking jobs dimension today, to examine and also validate format after that can begin make.
Day 34 : The majority of illumination jobs (altered from square downlight to round downlight) are done other than those in kitchen area and also bedroom (assumption is awaiting woodworking functions – kitchen area cupboard, master closet), frameless (we assumed is black framework) set panel was mounted. Opennet moving and also information factor.
Day 36: Send out the food preparation hob & hood over, acquired a collection of Aerogaz food preparation Hood & Hob at much less than $500. Obtained a cost-effective brand name and also version, unsure if we will certainly prepare regularly. Design: Hood AZ-9100 Black, Year 2021 New, Touch Panel, No switches, 900mm, coupled with Hob 790×500, black, solidified glass
Day 38: Talk To ID when can done and also handover (A: another month to finish all and also handover) Idea it will certainly be done quickly given that progression fairly well. Presume the hold-up is because of Covid-19 circumstance so woodworking job is postponed. No option however to wait… … …
Day 39 : Send out the black mixer and also black pipe over, to change the existing one (silver colour) in the usual shower room. New electric job done: moved the power indicate the left (also near the hood), customized master area brand-new power factor cord place, hid brand-new information factor electrical wiring. Step footwear shelf, cupboard and also drape track size.
Day 42 : Send out added shower room devices over. Preparation not to go to that constant hereafter given that it require another month to obtain the remodelling done… (ADD: DIDN’T KNOW THAT I WILL CERTAINLY MARVEL IN THE FOLLOWING SEE). Asked ID to take down the existing buzzer. Cooking area cupboard interior PVC picked earlier runs out supply, re pick one… On-going paint jobs
Day 47 : Last checked out 5 days back. Fairly unusual when I come today. Flooring security paper was eliminated, particles was gotten rid of, basic cleansing is finished……Seem like relocating currently!!! Scent major door paint, must be doing paint functions today…
Day 48 : Come with daytime today to examine the ceramic tile grouting, a whole lot obtained cleaned off after the cleansing. Planned to do noting however there are a lot of… might obtain the ID / professional to look at their very own… plaster retouch is provided for some small fracture at shower room box-up.